Makes sense to me that everybody should be aware of all POSSIBLY ANTICIPATED features/stories as soon as they exist, because you can then avoid doing work that later stories would contradict.

I'm not sure if I can see a negative consequence for having more stories "on the board". Physically of course the board might get full, but we use computers these days. That doesn't mean spend all your time planning and none implementing, but if you realize we will most like need a given feature in the end we should not hide that realization from the team.

An error (or oversight) in specifications is much more costly than an error in design or implementation, is the old Waterfall mantra, which I think is true. But Agile of course might not agree with that.

Maybe it would make sense to carry some kind of "Plan for the Future" throughout the process. Be aware of the anticipated features even though they are not fixed into the "plan" yet.



Having more (all) the tasks in a backlog from the get-go might make sense if we knew that: a) requirements wouldn't change b) priorities wouldn't change c) we would be able to keep the understanding of the work throughout the effort Then we'd just pull ticket by ticket and fill it with the details when we need it.

I've been doing it for 25 years, and I'm yet to see a project where the above assumptions would be true. I don't expect to see it.

Requirements always change. So do priorities.

We have this saying that our clients always know what they want. Until they see it. Then they know they wanted something different.

But even if that wasn't the case, the requirements change because we learn as we build the thing. The moment we know the least about a project is at its beginning. After that, we only know more.

So if things change, keeping more tickets in flight (even in backlog) means that every reprioritization, every planning, every pull to development costs more. Heck, we're bound to add work that's already there, but we forgot about it.

It's the cognitive load we add to so many activities every day.

And it doesn't even solve the problem of having better design because there's too much to remember.

Your intuition is right, though, when it comes to understanding the big picture. Not only architecture but also business. When every engineer on the team understands these higher-level goals it's so much easier to make sound decisions about design and implementation.

But for that we don't need dozens/hundreds of tickets in backlog.

BTW: I have a rule of thumb that on a physical board, there shouldn't be more than 100 items altogether. Our brains are incapable of meaningfully processing more. On a virtual board, it's even less, as our visual capabilities are impaired by screen limitations and crappy design of the tools we use.


FWIW, my rule of thumb was to avoid more than 3 cycles worth of stuff in view.

1) In Progress --> Started --> Completed: One cycle worth of WIP

2) Next Up: WIP for the next cycle (top third is highest priority, remainder is unknown priority until the cycle starts, these items are up for discussion)

3) Unscheduled backlog: Max count is less than 1 cycle worth of material

I've worked with small teams that can digest 5-10 "items/stories" in a cycle, for them there shouldn't be more than 30 items in view.

I've worked with larger teams that digested 30-40 items in a cycle and for them, seeing ~120 items was fine.

For larger teams, the work items tended to get broken down into smaller chunks as the communication overhead and carrying costs of implicit details was much higher.

How tactical, how coarse and how goal-oriented these work items are can vary widely by team/org interests and capabilities.


I think we could have "anticipated tasks" kept somewhere maybe not on the "board", and not being committed to (yet). Just raise awareness of what is the high-level view of where we are or might be going.

I agree that specifications always change. And that means it's good to be aware of what they might change to. Then we might more easily see how they might conflict with the current tasks, and thus in fact reduce the amount that specs would need to change in the future.


My argument is that forward looking ideas can be helpful, but they shouldn't be broken down into "tasks" until someone is prepared to make a concrete investment.


Looking out into the future is a great exercise and teams can and should discuss future facing ideas together with customers, design and product people. Having a general sense of why we're building what we're building is critical and does help inform the shape of what we build.

That said, the result of those discussions should be kept in a broad, narrative form that is focused on goals or outcomes. They should not generate multiple months-worth of concrete tasks that must be continuously curated, scheduled and negotiated.

In factory terms, this would look like quarterly or annual goals. One level higher than tactical activities.

"Stories on the Board" are more like raw materials that have been released and become Work in Process.

Overwhelming the line by pushing too much raw material has enormous, well-understood, negative consequences and usually results in far more waste than one can imagine.

Doing this well is hard and requires continuous balancing, and while there obviously isn't an exact rule that works for every context, there are thresholds at the edges that become pretty obvious with a little bit of experience and consideration.