Load shedding is an active measure taken when the grid operator knows that it will not be able to balance supply and demand. This is what happens in South Africa, where the operator preventively disconnects parts of the network at predetermined times to ensure network balance. As this is programmed, it is possible to rotate the areas under blackout.

In this case, we are dealing with a widespread grid incident. The various grid protection mechanisms have been triggered to prevent interconnection overload. In addition, the generators are trying to correct the grid frequency to exactly 50Hz. At 49Hz, more power must be generated; at 51Hz, less power must be generated. However, if the frequency varies too much, there are also protection mechanisms to prevent the turbines from overspeeding or amplifying frequency variations.

The grid is complex, and normally this type of incident is limited to one cell of the electricity distribution grid. A blackout is a domino effect, when a minor event triggers a chain reaction that disconnects more and more elements from the grid.

Th grid operator will have to restart or reconnect the power plants one by one, restore power to stations and sub stations. All of this must be done in a specific order before power can be restored to consumers. All of this takes time, requires resources (you need men on the ground), and the slightest error can lead to further outages.

Some consumers are prioritised, such as hospitals, transport infrastructure, telecoms and water networks. Many critical pieces of equipment have UPS systems, but these are not always designed for such long outages or have not been tested for years. There are patients with home equipment who will struggle.

This is why rotating load shedding is preferable. The outages are not too long and vital infrastructure is not affected (or less so).